Analysis Of Work Delay In Slum Quality Improvement Project Puday-Lapulu

  • Made Ardika Universitas Sulawesi Tenggara
  • Sufrianto Sufrianto Universitas Sulawesi Tenggara
  • Hujiyanto Hujiyanto Universitas Sulawesi Tenggara
  • Sitti Hawa Universitas Sulawesi Tenggara
Keywords: Keterlambatan, Pekerjaan, Proyek

Abstract

A construction project is an activity that aims to build facilities and infrastructure within the planned timeframe. The project can be defined as an organized effort or activity that uses the available budget and resources that must be achieved to achieve important goals, objectives, and expectations using the existing budget and resources, which must be completed within the planned timeframe so that the project does not experience delays. The purpose of this study was to determine how much work delays, the factors that cause work delays and how much influence the delay factors have on work delays in the Puday- Lapulu Slums Quality Improvement Project.

The results of this study indicate the value of SV is Rp. (- 8.25 %) While the value of SPI < 1 is 0.896 < 1, based on the criteria for the value of SV and SPI, it can be said that the work is late and has poor performance. Factors that influence delays are aspects of labor and materials. While the large influence of delay factors on work delays that is 10,9 %.

Downloads

Download data is not yet available.

References

Adhiputra, M. R. (2016). Analisis Faktor Penyebab Keterlambatan Proyek Konstruksi Jalan Tol (Studi Kasus: “Jalan Bebas Hambatan Medan-Kualanamu”). Skripsi. Fakultas Teknik Universitas Sumatera Utara.

Fanitawti, N. (2020). Pengaruh Tingkat Harga Dan Kualitas Produk Terhadap Keputusan Pembelian Bagi Konsumen Di Dapur Putih Cafe Metro. Skripsi. Fakultas Ekonomi dan Bisnis Islam Institut Agama Islam Negeri (Iain) Metro.

Hassan, H., Mangare, J. B., & Pratasis, P. A. (2016). Faktor–Faktor Penyebab Keterlambatan Pada Proyek Konstruksi Dan Alternatif Penyelesaiannya (Studi Kasus: Di Manado Town Square III). Jurnal Sipil Statik, 4(11).

Hidayat, W. (2019). Evaluasi Waktu Proyek Pada Proyek Pembangunan Ekstensi Gedung Magister Psikologi Fpsb Uii (Time Evaluation Project On The Fpsb Uii Ekstension Magister Psychology Building Project).

Ihsan, N. I., & Palapa, A. (2022). Pengaruh Karakteristik Individu Dan Komunikasi Interpersonal Terhadap Kinerja Crew Kapal Di Bawah Management PT. APOL. Majalah Ilmiah Bahari Jogja, 20(2), 142-152

Indrawati, P. S. (2019). Pengaruh Pemahaman, Kesadaran, Kualitas Pelayanan, Sanksi, Dan Sosialisasi Pajak Terhadap Kepatuhan Wajib Pajak Orang Pribadi Pada Kpp Pratama Candisari Semarang. Skripsi. Fakultas Ekonomi Universitas Semarang.

Johan, F. A. (2020). Analisis Earned Value Terhadap Biaya Dan Waktu Pada Proyek Pembangunan Gudang Farmasi (Earned Value Analysis Of Cost And Time In The Development Project Pharmaceutical Warehouse). Sripsi. Program Studi Teknik Sipil Universitas Islam Indonesia.

Muryanti, S. (2017). Pengaruh Rasio Aset Tetap Dibanding Total Aset, Umur Perusahaan, Dan Rasio Lancar Terhadap Profitabilitas Pada Perusahaan Farmasi Yang Terdaftar Di Bursa Efek Indonesia (Periode Tahun 2010-2015). Fakultas Ekonomi Dan Bisnis Universitas Brawijaya Malang.

Siswanto, A. B., & M, A. Salim. (2019). Manajemen Proyek. Semarang: CV. Pilar Nusantara. Ulfa. (2021). Analisa Kinerja Mandor Pada Proyek Pembangunan Gedung Di Kota Kendari.

Skripsi. Program Studi Teknik Sipil Universitas Sulawesi Tenggara

Yudhagama, F. (2020). Analisis Keterlambatan Proyek Pada Pembangunan Gedung Perpustakaan Uin Sunan Ampel Surabaya. Skripsi. Program Studi Teknik Sipil Fakultas Teknik Sipil Dan Perencanaan Universitas Islam Indonesia

Published
2023-04-29
How to Cite
Ardika, M., Sufrianto, S., Hujiyanto, H., & Hawa, S. (2023). Analysis Of Work Delay In Slum Quality Improvement Project Puday-Lapulu. Sultra Civil Engineering Journal (SCiEJ), 4(1), 43-54. https://doi.org/10.54297/sciej.v4i1.461